Chilled water from the campus loop will be use for the airconditioning. | . |
The chilled water supply enters Noyes Lab through the tunnel to RAL | . |
Pipes for the chilled water are put in the window on the 4th floor. 12/20/2005 |
|
12/20/2005 | |
12/21/2005 | |
Cooling water pipes in the ceiling of the 4th floor of Noyes Lab. 12/23/2005 |
|
Crane Operation between Natural History Building and Noyes Lab. Preparing to lift new air handling equipment and electrical equipment over the roof of Noyes Lab into the courtyard. 2/14/06 |
|
Air handling equipment over the north roof of Noyes Lab.
2/14/06 |
|
Air handling equipment coming down into courtyard of Noyes Lab 2/14/06 |
|
Air handling equipment being dropped into courtyard of Noyes Lab 2/14/06 |
|
Air handling equipment being brought into the building. 2/14/06 |
|
Air handling equipment in basement of Noyes Lab, formerly room 28b NL. 2/20/06 |
|
The a ttic above the north west corner of old Noyes Lab is being modified to take the new air equipment. 3/11/2006 | |
The roof on the north west corner of old Noyes has to be removed to put in the air handeling equipment. This is the first hole cut in the roof. 3/18/2006 |
|
Another view of the hole in the roof. 3/18/2006 | |
Steel to support the new roof. 3/23/2006 |
|
Section of the roof has been removed and steel installed. 3/23/2006 |
|
Interior view of roof. Steel beams support the new roof and the airconditioning equipment. 4/1/2006 |
|
Part of the roof from the old part of Noyes Lab that was removed to install air handeling units. 4/15/2006 |
|
A section of the roof has been covered to protect the building from rain. 4/15/2006 |
|
Interior view of the new roof on the north west section of old Noyes Lab. 4/22/2006 | |
Air handeling units installed in the attic of Noyes Lab. 4/22/2006 | |